During PI Planning, who negotiates the scope of a team's PI Objectives with the Business Owners?

  • AThe Release Train Engineer, on the team's behalf
  • BThe team, including its Product Owner, in direct conversation with the Business Owners(correct answer)
  • CProduct Management, before planning begins
  • DThe System Architect

Why

The conversation is the point. It is where a team learns which objectives the business actually values and where Business Owners learn what the work involves — neither of which survives being conducted through an intermediary.