PRINCE2 7: Management Products practice questions

37 questions on Management Products, one of the 6 areas assessed in PRINCE2 7 Foundation. Untimed, with an explanation after every answer.

mediumManagement Products

What are the three categories of management product in PRINCE2?

Ready for exam conditions? 60 questions, 60 minutes, 60% to pass.

Mock exam

A worked example

A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.

What is the purpose of a work package?

  • ATo record the project's overall scope
  • BTo define the work, products, constraints and reporting arrangements agreed between the Project Manager and the team delivering it(correct answer)
  • CTo document the products the project will hand over to the customer
  • DTo capture lessons for future projects

Why

A work package is the agreement at the boundary between controlling a stage and managing product delivery: what is to be produced, to what quality, within what constraints, and how progress will be reported. It is the mechanism through which the Project Manager delegates without losing control.

Practise a single PRINCE2 7 topic