PRINCE2 7: Practices practice questions

42 questions on Practices, one of the 6 areas assessed in PRINCE2 7 Foundation. Untimed, with an explanation after every answer.

easyPractices

How many practices does PRINCE2 7 define?

Ready for exam conditions? 60 questions, 60 minutes, 60% to pass.

Mock exam

A worked example

A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.

What is the purpose of the business case practice?

  • ATo secure the project's funding at the outset
  • BTo establish mechanisms that judge whether the project is, and remains, desirable, viable and achievable(correct answer)
  • CTo document the project's costs and benefits for audit
  • DTo define the products the project will deliver

Why

The business case practice exists to keep justification under continuous test against three criteria — desirable, viable and achievable — throughout the project, not just at approval. That continuous testing is what supports the continued business justification principle. Funding (A) and audit records (C) are consequences rather than the purpose.

Practise a single PRINCE2 7 topic