Which SAFe Lean-Agile principle most directly explains why work should be released in small batches?
Ready for exam conditions? 45 questions, 90 minutes, 73% to pass.
Mock examA worked example
A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.
An Agile Release Train consistently plans to 100% of its capacity every Planning Interval and consistently misses its objectives. Which Lean-Agile principle is being violated?
- ABase milestones on objective evaluation of working systems
- BAssume variability, preserve options(correct answer)
- CUnlock the intrinsic motivation of knowledge workers
- DApply systems thinking
Why
Planning to full capacity assumes no variability, and knowledge work always has some. Queueing behaviour is non-linear: utilisation near 100% makes wait times rise sharply, so the train has removed its own ability to absorb the unexpected. Preserving capacity is preserving options.