What is the purpose of the Inspect and Adapt event?

Ready for exam conditions? 45 questions, 90 minutes, 73% to pass.

Mock exam

A worked example

A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.

According to the SAFe implementation roadmap, what should happen before launching the first Agile Release Train?

  • AEvery team should be certified in SAFe
  • BReaching the tipping point, training Lean-Agile change agents and executives, identifying value streams and ARTs, and preparing for ART launch(correct answer)
  • CThe organisation should restructure its reporting lines
  • DA pilot project should be completed by a single team

Why

The roadmap sequences the change: reaching the tipping point, training change agents and leaders, identifying value streams and ARTs, then creating the implementation plan and preparing for launch. Leadership engagement comes first because SAFe adoption fails most often for lack of it, not for lack of team-level training (A) or a successful pilot (D).