According to the SAFe implementation roadmap, what should happen before launching the first Agile Release Train?
- AEvery team should be certified in SAFe
- BReaching the tipping point, training Lean-Agile change agents and executives, identifying value streams and ARTs, and preparing for ART launch(correct answer)
- CThe organisation should restructure its reporting lines
- DA pilot project should be completed by a single team
Why
The roadmap sequences the change: reaching the tipping point, training change agents and leaders, identifying value streams and ARTs, then creating the implementation plan and preparing for launch. Leadership engagement comes first because SAFe adoption fails most often for lack of it, not for lack of team-level training (A) or a successful pilot (D).