What is an Agile Release Train?
Ready for exam conditions? 45 questions, 90 minutes, 73% to pass.
Mock examA worked example
A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.
What is the primary accountability of the Release Train Engineer?
- AManaging the delivery schedule and holding teams to their commitments
- BActing as a servant leader and chief Scrum Master for the train, facilitating its events and processes and removing impediments(correct answer)
- COwning the ART Backlog and prioritising Features
- DLine-managing the Scrum Masters on the train
Why
The RTE is the train's servant leader and chief Scrum Master: facilitating PI Planning, the ART sync events and the Inspect and Adapt workshop, and escalating impediments the teams cannot resolve. Holding teams to commitments (A) is a command-and-control reading, the ART Backlog belongs to Product Management (C), and the RTE is not a line manager (D).