What is the primary output of PI Planning?

Ready for exam conditions? 45 questions, 90 minutes, 73% to pass.

Mock exam

A worked example

A question from the bank with its answer and the reasoning behind it. Every practice question comes with an explanation like this one.

During PI Planning, a Scrum Master's team identifies a dependency on another team that would block its second iteration. What should the Scrum Master do?

  • ARecord it as a risk to be resolved after PI Planning
  • BTake it to the other team during the breakout, agree the sequencing, and make it visible on the program board(correct answer)
  • CEscalate it to the Release Train Engineer to resolve
  • DRe-plan the team's work to avoid the dependency entirely

Why

Surfacing and resolving cross-team dependencies face to face is the main reason PI Planning gathers everyone in one place. Teams negotiate directly during the breakouts and record the agreement on the program board. Deferring it (A) wastes the opportunity, escalating first (C) skips the decentralised decision, and avoiding the dependency (D) may sacrifice the most valuable work.